LMUD
requires an Application
for Service be completed on every new agricultural pump
project. Also, if you are planning to replace or “upgrade”
your existing electrical panel on your pump, this application should
be completed as well.
Included
in the application is a Load
Planning Sheet.It is important that this form be filled out
as completely as possible with all the electrical equipment that
your project will utilize. This
information will help us in providing you a more reliable source
of electricity. Some questions on this form may be a little
confusing. Therefore, we
suggest that a qualified electrician help you complete the form. A Plot
Plan of the installation site must accompany the application
as well.
It
is very important that you plan ahead for electrical service to
your pump. During peak
building season, please plan on 4 to 6 weeks from the time an application
is received in our office to the time the design is completed and
information is provided to you.
Actual construction of your project is scheduled after
this time. It is important to contact the City of Susanville
or Lassen County
building departments in advance for a construction permit. Also,
these agencies will provide you with information whether your utilities
can be installed overhead or underground.
If
you have any questions, please feel free to call us and ask for
our New Business Representative.